primitive questions contractor
« on: April 28, 2013, 09:32:00 AM »
http://www.democraticunderground.com/11581967

Oh my.

A primitive in a pickle.

Quote
Ruby the Liberal (23,420 posts)    Sat Apr 27, 2013, 05:51 PM

Question on dealing with contractors

I have one currently working on my house who is giving me bids as he goes and is fixed price. Reasoning for this is because of hidden damage that couldn't be quoted until demolition was done (yep - I had rotted floor joists).
 
So in one of these bids, he cites the shower repair as "install shower base" and at the bottom, it says "Labor and material cost $2,200"
 
That was dated April 6th. On March 5th, I gave him a check for $1,000 to buy the shower base because of the lead/shipping time.
 
Now, he is telling me that "oops", he forgot to include that in "materials" in the $2,200 bid because I gave him a check in advance.
 
Questions:

Any recommendations on how to handle this?

Does $3,200 even sound reasonable for a shower base, drain, greenboard, membrane and plumbing behind the walls? Quote specifically does not include faucet and tile work. This is a 4x5 walk-in shower with no door.
 
It is reasonable to ask for receipts from the "materials" on a fixed bid project where something has been claimed as being missed?

Quote
OffWithTheirHeads (9,018 posts)   Sat Apr 27, 2013, 06:41 PM

1. Depends on where you live.

If you are in the SF Bay area, that's probably cheap. If you are in Tucson, not so much. You don't ask for reciepts cause he is buying wholsale and selling to you retail. That is part of his profit margin and you probably couldn't buy at his price anyway.

Quote
Ruby the Liberal (23,420 posts)    Sat Apr 27, 2013, 06:48 PM

2. Thanks for the heads up.

Northeast, about 1/2 the cost of living as Central NJ.

Not worried about his profit margin - he has been telling me all along what things are costing with his 25% discount as he is asking me to choose between options A and B. He has been upfront about his markup.
 
I guess my concern is that I have a fixed bid for price X that is now "I forgot/misquoted" and he wants to add a time & materials element to it because he screwed up and forgot something - from almost 2 months ago. Is it reasonable to request proof of cost when one fixed bid (of 12 for this project) needs to be changed to T&M after the fact?

This probably could've been avoided if the primitive had hired a union contractor.

Quote
Wash. state Desk Jet (1,850 posts)    Sat Apr 27, 2013, 08:19 PM

3. I don't think he forgot anything.

I think he elevated his bid because he figures you will go for it.

Nobody is off by a thousand or more.

Nobody. It might just be what you call bait & trap. when one works on time and materials on a contract bid ,one also must know how to estimate time and materials in and including the unforeseen -,experience is how that plays out. either there is a lack of that or he's baiting ya.
 
I could be wrong ,but somehow I don't think so.

Sometimes slippery contractors use the unforeseen factor to raise the bid up into the sky-bid low to get the job than raise the bid -,the unforeseen-that which one cannot bit across is the avenue they use to elevate the cost.
 
I think you better stop with that befor it goes too far. If you are committed to the shower floor than stop with further bids until it is done than bring in other contractors to bid on the rest.

Or tell him to get it right or just get.

Look over your contract agreement in legal terms.

And then the always-helpful Hussein von Slobber pops in:

Quote
Hassin Bin Sober (8,555 posts)    Sat Apr 27, 2013, 09:37 PM

5. Is he pouring a concrete shower base or installing a pre-made pan?

What system is he using? If you know.

You mention membrane. Is that membrane for walls or shower pan?

Quote
Ruby the Liberal (23,420 posts)   Sun Apr 28, 2013, 01:55 AM

8. Heya HBS

He purchased a Schluder modifiable base and Schluder Kerdi membrane, greenboard drywall and generic pipes. Membrane was for the walls only (the base just needed thinset). Shower is just under 4x5.

Quote
Hassin Bin Sober (8,555 posts)   Sun Apr 28, 2013, 08:11 AM

12. That makes a little more sense re: $1000 for materials.

The good news is that is a state of the art system for building showers. So we know you are dealing with someone who knows how to build a shower. That Kerdi stuff is suitable for a steam shower and will keep the moisture AND water inside the shower where it belongs.
 
I can't tell you how many nightmare stories I've seen or read about regarding poorly constructed showers that leak and turn moldy because the installer had no idea how to build a leak-proof shower. Apparently there are still people out there who think tile and grout are meant to stop water from migrating to your floor and walls.
 
I always say I would never but a home with a walk in shower unless I saw it built. I had a client almost buy a condo with three walk-in showers. They moved in and didn't close due to financial troubles with the builder - by the time they moved out six months later, every shower was leaking. I used to think tubs with showers were kind of dummy-proof but I just replaced a tub for a friend in a ten year old condo. The tub (and drywall below) had been "repaired" over and over since the condo was purchased.
 
When I heard $1000 dollars for material, I thought that was really steep for some dry pack mortar (4 bucks a bag) and a $60 dollar pan liner. But I know that Kerdi stuff is expensive. And that is a good sized shower.
 
Not sure what to tell you regarding his oops/price. I'm of two minds on the subject. I've been on both sides of the equation and can understand mistakes and mis communications happen. I also know there are unscrupulous contractors that like to play games.
 
I suppose you could always bring in another contractor to give you a price for a similar build. That could get messy. Especially if you can't find another Kerdi guy.
 
You could also post over at the John Bridge tile forums. There are a bunch of pros over there who do Kerdi. In fact, it's their favorite system. They are a REALLY friendly bunch over there.

Quote
Ruby the Liberal (23,420 posts)    Sun Apr 28, 2013, 08:38 AM

13. Yikes!

Okay, that makes me feel better.

Still having trouble making the leap from $2,200 to $3,200 though. If the base + membrane are $1k (that I prepaid in March), is there a possible justification for $2,200 for greenboard, pipes and labor to put it all together? Thats what I am not connecting. It isn't even full walls as one of the walls is glass block (which is a seperate quote).
 
I really appreciate the opinion on the Schluder Kerdi. According to Zillow, I am $130k upside down on this house and wouldn't have even done this if it wasn't for the mold issue. Sounds like that was the right choice, but no one will ever know. LOL!
 
I appreciate your help. I am going to be talking to him this afternoon and just want my head straight before I address this.

Quote
mbperrin (6,680 posts)    Sat Apr 27, 2013, 10:11 PM

6. Tell him the oops belongs to him, and he will need to eat that.

It's minor, since there are multiple jobs as you move along, and he can do it or walk, and truly don't care which.
 
I was in the remodeling business for 15 years, until I wore my shoulders out, and not on any job, small or large, including a 2600 square foot house built along the Colorado River, did I ever take one dime up front for materials and labor. I quoted a firm price, and when the job was done to both our satisfactions, we got paid the agreed amount.
 
Truthfully, anyone who can't front their own materials is too small-time for me to trust my home to. If they're that short, how can they buy insurance or account for errors? If he does not agree to stand by his original bid, I'd run him off, and we'd be even right where we stand.
 
Otherwise, it's the camel's nose. I can't tell you how many jobs I finished up that others started over the years we were in business. And I enjoyed the work, but when I could no longer do it, we had to release about 18 months' scheduled work for some really nice people.
 
Many may find my position extreme, but it's really just expecting him to abide by his own expertise. If an honest error, he'll learn, and it certainly won't break him. If a dishonest scheme, you're better off without him.
 
Just my 2 cents.

Quote
Wash. state Desk Jet (1,850 posts)    Sun Apr 28, 2013, 12:19 AM

7. A bit too extreme !

That is a bit extreme. Contract bids are broken down into phases . Demo is the first phase as a rule. A check comes at the completion of each phase .you will find that a common place where banks are part of the it-say for example the loan agreement. That's how it's done.
 
Your way ,what if it's a very big job and yer in it for $50.000 or more,the clients go broke and file for devoice ? As this was happening they add on a lot material wise just because they feel like it.
 
What do you do with yer loss ?Do you eat it and move on ? does yer family go without because yer credit card bills require payment and int rest ?
 
A well written contract agreement covers both the client and the contractor.

You know you get into 1700 square feet two floors 40 offices and on the remodel lighting alone and cost oh,say $12,000 or more. That's just the lighting materials. 1700sq.ft is the roof !

so thats a lot of building !

And paint and carpet and building and demo,tile on and on -man that adds up.

They hire independents to save money . Independents don't have 3-million or more operating capital. !
 
And it is a well know fact on the client end that independents don't have a huge overhead that is included in the bill .
 
When the loan is $50,000 or less the bank as rule leaves it to the applicant to pay the contractors/contractor.However in some cases those banks want to see how it's being spent if it's a home upgrade improvement. If thats the case the money is released in phases upon completion.Bids are broken down into phases-4 or five or as many dependant upon the length of the project. I mean the client will end up paying the int rest on the credit card buy's,you got to know that.
 
and you run up big bills with those suppliers and they call in demand payments don't they ?

The educated homeowner in the remodel game knows how it works.

There has to be trust between the client and the contractor.

That might have to do with people asking people if they know any good trust able contractors !

Quote
mbperrin (6,680 posts)    Sun Apr 28, 2013, 03:30 AM

10. In 15 years, I never had a client fail to pay in full what they owed.

In return, we never failed to finish a job. We didn't do giant jobs - the biggest we ever did was a nice vacation cabin for a little over $320,000 20 years ago.
 
We always had the cash reserve to do any job we bid - I never charged a dime of supplies, and I haven't banked since 1978. None of our clients required a bank loan - they paid on completion. Never dealt with commercial people at all - their dishonest ways are just not for me, and I knew that ahead of time.
 
Our contracts were very simple - the client knew what they had, and they knew what they wanted to end up with, so I bid a dollar amount to do that - quite pointless to break it up into some imaginary categories of supposed materials costs which differ from real, and disguise labor as materials and all that. They needed to know how much money and how much time.
 
I worked with my grandfather as a young man, and he worked until he was 86, crawling under houses and in attics. When he died, he had a three year waiting list of people who wanted him to do their jobs. He made it simple for them.
 
Now perhaps things are just different elsewhere, but in this part of the country, you do what you say, and if you're not bright enough or experienced enough to do that, work for someone for wages. I do act in an extreme way, because these are people coming into your home and altering where you live, forever. I don't need some amateurs or trainees to do that - I need someone who will get it done, on time and for the dollars agreed. Worked here for my grandfather and for me. I just had the misfortune to wear out my shoulders - I can't lift my hands much higher than my head and for just a few minutes at that, or I'd still be working at that - it's a good job, a real puzzle, and never a dull moment.

Quote
Ruby the Liberal (23,420 posts)    Sun Apr 28, 2013, 02:08 AM

9. Thank you for adding your thoughts/experience to this dilema.

I am an MBA and my initial inclination was "sorry for your luck in that you chose to fixed bid rather than time/materials".
 
Then again, I get honest mistakes and don't want to screw the guy over. I just don't know enough about quoting this stuff to know if he is telling me the truth.
 
This project was estimated at $10k (barring unforseen hidden damage - the reason for the work being mold) and a months worth of work. Project started on March 18 and tile just started going up Friday and is at $19,000 and counting. Twice the price and twice the time is taking its toll (going to the gym every AM to shower in public for 2 months doesn't help matters) but I want to do right by this guy.
 
Appreciate you weighing in. As I recall, you own multiple rental properties - thanks for your thoughts.

Quote
mbperrin (6,680 posts)   Sun Apr 28, 2013, 03:34 AM

11. Sorry you're having trouble at all.

Sorry if I came on too strong, but I really do have a peeve about people who make remodelers look bad. We do own a number of properties, and customer satisfaction is really important there, too.
apres moi, le deluge

Milo Yiannopoulos "It has been obvious since 2016 that Trump carries an anointing of some kind. My American friends, are you so blind to reason, and deaf to Heaven? Can he do all this, and cannot get a crown? This man is your King. Coronate him, and watch every devil shriek, and every demon howl."

Offline Dori

  • Hero Member
  • *****
  • Posts: 7964
  • Reputation: +406/-39
Re: primitive questions contractor
« Reply #1 on: April 28, 2013, 09:58:55 AM »
Duh....call another contractor and ask for a ball-park price on the same system if you don't trust this guy.





“How fortunate for governments that the people     they administer don't think”  Adolph Hitler

Offline Conservative Libertarian

  • I'm not being mean. You are just a sissy.
  • Hero Member
  • *****
  • Posts: 1301
  • Reputation: +150/-32
Re: primitive questions contractor
« Reply #2 on: April 28, 2013, 10:15:01 AM »
Duh....call another contractor and ask for a ball-park price on the same system if you don't trust this guy.







It demonstrates that DUmmies don't understand the concept of competition and its potential for yielding the best results for the consumer.
It takes a FAMILY to raise a child--Not Hitlery Klinton's Socialist, Anti-Family, Nanny-State...I mean, "Village".

Offline franksolich

  • Scourge of the Primitives
  • Global Moderator
  • Hero Member
  • *****
  • Posts: 58722
  • Reputation: +3102/-173
Re: primitive questions contractor
« Reply #3 on: April 28, 2013, 10:16:48 AM »
Duh....call another contractor and ask for a ball-park price on the same system if you don't trust this guy.

I still think the big mistake was not hiring union labor.
apres moi, le deluge

Milo Yiannopoulos "It has been obvious since 2016 that Trump carries an anointing of some kind. My American friends, are you so blind to reason, and deaf to Heaven? Can he do all this, and cannot get a crown? This man is your King. Coronate him, and watch every devil shriek, and every demon howl."

Offline Dori

  • Hero Member
  • *****
  • Posts: 7964
  • Reputation: +406/-39
Re: primitive questions contractor
« Reply #4 on: April 28, 2013, 10:29:38 AM »
I still think the big mistake was not hiring union labor.

At three times the cost.

I did the books for a construction contractor for 7 years.  Actually it was two, a partnership.  They were great, did quality work at fair prices.  They missed out on a lot of local government jobs, because they didn't hire union employees.

It's disgusting what states and cities pay for construction when they can get the same, or better, from their local businessmen.

That's pretty much the same thing I found to be true when I moved my kids out of public school to private.  About a third of the cost.

“How fortunate for governments that the people     they administer don't think”  Adolph Hitler

Offline franksolich

  • Scourge of the Primitives
  • Global Moderator
  • Hero Member
  • *****
  • Posts: 58722
  • Reputation: +3102/-173
Re: primitive questions contractor
« Reply #5 on: April 28, 2013, 10:33:25 AM »
At three times the cost.

I did the books for a construction contractor for 7 years.  Actually it was two, a partnership.  They were great, did quality work at fair prices.  They missed out on a lot of local government jobs, because they didn't hire union employees.

It's disgusting what states and cities pay for construction when they can get the same, or better, from their local businessmen.

That's pretty much the same thing I found to be true when I moved my kids out of public school to private.  About a third of the cost.

Yeah, I know, madam, but I'm trying to remind the primitives of their obligation to hire union labor.

The primitives always make a big deal about supporting union labor, but then they turn around and hire cheaper non-union labor or even worse, guys who're paid cash.

Apparently you and I are supposed to hire union labor, while the primitives can hire cheaper labor.
apres moi, le deluge

Milo Yiannopoulos "It has been obvious since 2016 that Trump carries an anointing of some kind. My American friends, are you so blind to reason, and deaf to Heaven? Can he do all this, and cannot get a crown? This man is your King. Coronate him, and watch every devil shriek, and every demon howl."

Offline JohnnyReb

  • In Memoriam
  • Hero Member
  • *****
  • Posts: 32063
  • Reputation: +1998/-134
Re: primitive questions contractor
« Reply #6 on: April 28, 2013, 12:29:59 PM »
DUmmie putting in a shower?.......for what?
“The American people will never knowingly adopt socialism. But, under the name of ‘liberalism’, they will adopt every fragment of the socialist program, until one day America will be a socialist nation, without knowing how it happened.” - Norman Thomas, U.S. Socialist Party presidential candidate 1940, 1944 and 1948

"America is like a healthy body and its resistance is threefold: its patriotism, its morality, and its spiritual life. If we can undermine these three areas, America will collapse from within."  Stalin

Offline Conservative Libertarian

  • I'm not being mean. You are just a sissy.
  • Hero Member
  • *****
  • Posts: 1301
  • Reputation: +150/-32
Re: primitive questions contractor
« Reply #7 on: April 28, 2013, 01:02:55 PM »
DUmmie putting in a shower?.......for what?

 :rotf: :rotf:

They have to wash out their bongs from time to time. They can't take them outside and risk being seen by the authorities.
It takes a FAMILY to raise a child--Not Hitlery Klinton's Socialist, Anti-Family, Nanny-State...I mean, "Village".

Offline I_B_Perky

  • Hero Member
  • *****
  • Posts: 7532
  • Reputation: +721/-329
Re: primitive questions contractor
« Reply #8 on: April 28, 2013, 10:14:22 PM »
Hey dummie? Got a million dollars worth of advice for free.

Ask Nads. She has probably done it herself and can tell you everything you need to know.