Building a Workshop / Shed. Design was for a 6m x 6m secure concrete area as a workshop and storm shelter , attached to a 6m x 6m semi-enclosed area as a car/boat storage and rigging / loading / dirty work area.
Ground Breaking.
Forming 6m x 12m slab and adding steel. The 6 Large (650mm x 1000mm) piers down one side are hard to spot. These were required because of the proximity to a sewer line.
Pour and smooth the slab.
Next phase was to lay blocks with a double bond beam up top and core fill for the walled section. Most people are satisfied with filling every 4th core - I filled the lot. Then render inside and out.
Install C section purlins and roofing iron. Construct and hang exterior gates.
Then do some basic internal fitout.
Still to come - Installing a roller door and window, screening off the open part of the building - more internal fitout , hang door and install a water tank. That's next week.